Supreme Court Limits Ability of Groups
to Bring Citizen Suits
for the Recovery of Civil Penalties
In an important decision issued on March 4,
the U.S. Supreme Court ruled that a party
lacks standing under Article III of the
Constitution to bring a citizen suit to recover
civil penalties unless the party can also show
that it is entitled to injunctive relief to remedy
a concrete injury to itself. The Court's
decision was issued in Steel Co. v. Citizens For
A Better Environment (S.Ct. No. 96-643),
which involved a company's failure to file
certain reports under the Emergency Planning
and Community Right-To-Know Act
(EPCRA).
The Court's broad ruling will have a
substantial impact on the ability of groups to
bring citizen suits under the Clean Air Act as
well as all other environmental statutes with
citizen suit provisions. Because the ruling was
based on fundamental constitutional
principles, not the statutory language of
EPCRA, its scope is not in any way limited to
EPCRA citizen suits. The decision establishes
that a party may not bring a citizen suit for
civil penalties under the environmental
statutes unless it can allege and ultimately
prove that it is entitled to injunctive relief
based on the existence of "a continuing
violation or the imminence of a future
violation."
Amicus Curiae Brief Filed by Clean
Air Implementation Project
The Clean Air Implementation Project
(CAIP) filed an amicus curiae brief before the
Supreme Court because of the potential
significance of the Court's ruling on Clean Air
Act citizen suits. In ruling below that
EPCRA citizen suits could be brought based
on "wholly past" violations, the Seventh
Circuit had specifically pointed to the Clean
Air Act citizen suit provision as
demonstrating Congress' intent that such
actions be allowed. CAIP's brief
maintained that the Clean Air Act citizen suit
provision should not be interpreted in the
expansive manner suggested by the Seventh
Circuit and that parties have standing to bring
citizen suits only if they can demonstrate that
they are entitled to injunctive relief to remedy
an ongoing compliance problem.
In particular, CAIP's amicus curiae
brief sought to focus the Supreme Court's
attention on the following points:
Under the Clean Air Act, there is the
potential for massive numbers of
citizen suits to be filed seeking
substantial civil penalties where no
real compliance problems exist.
If the Court were to consider the
Clean Air Act citizen suit provision
relevant to its analysis of EPCRA, the
Act "should . . . be interpreted only to
authorize the filing of citizen suits to
recover civil penalties for past
violations that are ongoing, i.e.,
violations which are virtually certain
to recur and require injunctive relief to
compel compliance." The brief
analyzed the language of the Clean Air
Act citizen suit provision and showed
that Congress intended to impose civil
penalties only where injunctive relief
is necessary. The brief further noted
that a number of district courts have
erroneously held that citizens can
bring actions to recover civil penalties
for "wholly past" violations under the
Clean Air Act, i.e., violations which
would not entitle the plaintiffs to
injunctive relief.
In the case before the Court, the
violations were cured between the
time the 60-day notice of intent to sue
was sent and the complaint was filed.
For that reason, there was concern
that the Court might narrowly hold
that citizen suit actions involving the
failure to comply with the reporting
requirements of EPCRA are
impermissible because they are
"wholly past" violations, without
clarifying the conditions under which
citizen suits for civil penalties could be
brought. Accordingly, the brief
emphasized that the Court should
broadly rule that citizen suits for civil
penalties may be brought only where
violations are ongoing or likely to
recur.
Under Article III of the Constitution,
citizens lack standing to bring suit
unless violations are ongoing or likely
to recur, because they otherwise
cannot demonstrate that the action
will redress an injury-in-fact. The
brief maintained that, in view
of the Article III requirement
to demonstrate the existence of
an injury that can be redressed,
a citizen must establish that it
is entitled to injunctive relief
before it may seek to recover
civil penalties or obtain other
relief.
The Supreme Court's Decision
Writing for the majority, Justice Scalia
first concluded that the Court must address
the constitutional standing issue before
determining whether the language of EPCRA
authorized a court to consider an action based
on wholly past violations. In a separate
opinion concurring in the judgment, Justice
Stevens argued that the question of whether
EPCRA authorized citizen suits for wholly
past violations was a jurisdictional issue and
that the Court should have considered that
statutory authority issue first, thereby making
it unnecessary to rule on the constitutional
standing issue. Three other Justices also filed
separate concurring opinions in which they
took different positions on whether and to
what extent the Court was required to address
the constitutional standing issue first. In the
end, all nine Justices concluded that the
Seventh Circuit's decision should be reversed,
although they disagreed in varying degrees as
to the reasons why.
Having determined that the Court
must address the issue of standing before
proceeding further, Justice Scalia ruled that the
citizens group lacked standing under Article
III because it had not satisfied the
"redressability" requirement for establishing
standing. (The Court did not actually
determine whether the injuries alleged by the
group would have constituted sufficiently
concrete injuries because it concluded that
they would not be redressable in any event.)
Justice Scalia's opinion analyzed the items of
relief sought by the group and rejected each as
a basis for redressing the group's claimed
injuries:
Declaratory relief Although the
plaintiff had sought a declaration from
the district court that the company
had violated EPCRA by not filing the
reports, the majority opinion stated
that this would not help the plaintiff.
The opinion stated that, since there
was no controversy regarding whether
the reports had been filed or whether
violations had occurred, such
declaratory relief would have no
impact.
Recovery of civil penalties The
majority opinion concluded that an
order awarding civil penalties would
not redress any injury to the plaintiff
because the penalties would be paid to
the Treasury. To the extent the
plaintiff claimed that it had an interest
in the penalties being paid in
accordance with the statute, the
opinion held that this merely
constituted an "undifferentiated public
interest" in carrying out the laws -- an
interest which the Court previously
had held is not a cognizable injury for
Article III purposes.
Recovery of investigation costs
Although the group had contended
that it had been injured because it had
expended funds to investigate the
company's EPCRA compliance
problems, the Court ruled that the
expenditures were not an injury to be
redressed in a citizen suit. The Court
explained that such investigation costs
could be recovered only if authorized
by the citizen suit provision. In
relevant part, that provision authorizes
recovery of litigation costs but is silent
as to pre-litigation investigation costs.
However, even if the investigation
costs were considered to be litigation
costs, the group would lack standing
because the Court has previously ruled
that the expenditure of litigation costs
is not sufficient, by itself, to give a
party Article III standing to continue
pursuing a federal court action.
Request for injunctive and other relief
The Court rejected the group's
contentions that its requests for an
order directing the company to allow
inspections by the group and to
provide copies of reports to the group
were adequate to establish standing.
The Court ruled that the allegations of
the complaint were insufficient to
show that this requested relief would
redress any injury suffered by the
group.
The majority opinion's discussion of
the group's request for injunctive relief
provided the single most important
element of the Court's decision.
Although the Court acknowledged
that a request for injunctive relief
could satisfy the redressability test, it
concluded that injunctive relief could
only be proper where the plaintiff has
alleged the existence of "a continuing
violation or the imminence of a future
violation." The Court stated that,
otherwise, the plaintiff's interest is
merely a "generalized interest in
deterrence, which is insufficient for
purposes of Article III." In short, the
Court has made clear that allegations
based on past violations that are not
continuing or are not likely to recur
are insufficient to establish Article III
standing to bring a citizen suit under
the environmental statutes. Thus, in
order to establish its standing to bring
suit, a plaintiff seeking civil penalties
under a citizen suit provision must
allege and demonstrate entitlement to
injunctive relief based on an ongoing
compliance problem.
Stakeholder Discussions on
Part 70 Permit Revisions
Continue
The Title V "small stakeholder group"
convened last summer by EPA to address
Part 70 permit revisions issues is continuing its
discussions with the Agency. However,
progress has been much slower than expected.
The latest indications are that EPA will
probably not promulgate a final rule revising
Part 70 until mid-1999 at the earliest. EPA
recently announced that it is establishing a
new public comment period for those portions
of its draft final rule that do not involve the
permit revisions sections. These developments
are discussed below.
Status of the Small
Stakeholder Process
On May 14, 1997, EPA released a draft
Part 70 rulemaking package for review and
public comment by interested parties. The
draft rule would have created a permit
revisions scheme that differed from EPA's
August 1995 supplemental proposal in ways
that caused great concern for both industry
and states. In particular, the draft rule would
have created a three-tiered scheme under
which most changes would fall into the
"middle" or "minor revisions" tier and would
likely be subject to substantial delays under
the proposed review procedures.
In light of the negative reactions to the
May 1997 draft rule, EPA agreed to attempt to
develop a more acceptable permit revisions
scheme. To help achieve this goal, EPA
convened a small stakeholder group to
discuss possible approaches to improving the
permit revisions scheme. This group
generally consisting of six industry
representatives, five state and local agency
representatives, and one environmental
group representative -- has met with EPA
representatives at various times since June
1997.
Industry and state representatives
believed that significant progress was being
made in the early stages of the stakeholder
discussions. For example, EPA
representatives agreed to limit the kinds of
changes which fall into the middle tier and
to allow for "post hoc" review of changes
falling into the middle tier.
However, certain key issues have still
not been resolved, and it is unclear whether
mutually acceptable approaches can be
agreed upon. Among the principal points of
disagreement are:
Major netouts Under the scheme
being considered, major netouts would
fall into the "significant revisions" tier
while minor netouts would fall into
the "minor revisions" tier. The
principal issue that remains is how
netouts are to be defined. According
to EPA, a major netout occurs
whenever emissions increases
associated with a project (without
consideration of project decreases)
exceed the major source threshold
level. (A minor netout occurs when
the project increases exceed the
relevant significance threshold.)
Industry has emphasized that it is
important that netouts be defined in
terms of the "project net," i.e.,
emissions decreases associated with the
project should be considered along
with emissions increases in
determining whether the threshold has
been exceeded. State representatives
have supported this position.
Although EPA originally seemed to
accept this approach, EPA stated in
February that it wanted to consider
only project increases in determining
whether the relevant threshold has
been exceeded.
Trial operation period The state and
industry representatives have proposed
that a source have up to 270 days after
issuance of a construction permit in
which to operate before obtaining its
Title V permit. However, EPA has
contended that section 502(a) of the
Act precludes this approach, because
the source would not have a Title V
permit covering the changes associated
with the project. EPA has suggested a
compromise under which EPA would
have an opportunity to object to
proposed permit terms during the
construction permit comment period
rather than solely during the operating
permit issuance phase. There appears
to be no resolution immediately in
sight.
Potential to emit (PTE) limits PTE
limits are source-specific limits that are
taken to restrict the source's PTE for
purposes of "major source" or "major
modification" determinations. The
principal issue concerns whether, and
to what extent, PTE limits will fall
into the "minor revisions" tier rather
than the "de minimis revisions" tier.
EPA has proposed various approaches
for defining PTE limits that must be
processed as minor revisions. For
example, some EPA representatives
have suggested that PTE limits that are
as low as 50 percent of the relevant
threshold level may not be treated as
"de minimis revisions."
New Comment Period on the
Remainder of the Draft Rule
On March 25, EPA published a Federal
Register notice announcing the availability of
a draft preamble and draft regulatory sections
addressing Part 70 matters other than permit
revisions or public and EPA review. 63 Fed.
Reg. 14,392. The matters addressed include
definitions, applicability, permit programs,
permit applications, and permit content. The
draft sections available for review "are the
same as those contained in the May 14, 1997
draft preamble and regulatory revisions." The
notice further states that the sections are being
made available for comment at this point so
that any public comments may be considered
before the close of the stakeholder discussions.
The public comment period will end on April
24, 1998.
Although industry and states have
primarily focussed their efforts on improving
the permit revisions sections of Part 70,
certain of the remaining provisions of the
rulemaking package are potentially very
important as well. Among the principal issues
arising in connection with the draft sections
are ones associated with the Part 70 definition
of "major source" as it relates to such matters
as support facilities, research and development
facilities, and fugitive emissions. Other
significant issues relate to the Part 70
compliance certification requirements and
emergency defense provisions.
EPA Issues New Guidance for
Permit-related Environmental
Justice Claims
On February 5, EPA issued an "Interim
Guidance for Investigating Title VI
Administrative Complaints Challenging
Permits" to establish the ground rules for
EPA's investigation of citizen complaints that
state or local permitting actions violate Title
VI of the Civil Rights Act of 1964. The
guidance will likely lead to citizens groups
raising more environmental justice claims,
especially in the context of air, water and
waste permitting actions.
Title VI of the Civil Rights Act
prohibits discrimination on the basis of race,
color or national origin. Under EPA's
regulations implementing Title VI, recipients
of EPA funding (which include states and local
environmental agencies) may not use "criteria
or methods . . . which have the effect of
subjecting individuals to discrimination
because of their race, color, national origin or
sex. . . ." 40 C.F.R 7.35(b). EPA's
implementing regulations appear to prohibit
actions that simply result in a discriminatory
effect or "disparate impact" on racial or ethnic
minorities, regardless of intent.
The interim guidance document
confirms that it is the Agency's position that
citizens may file Title VI complaints with
EPA alleging that discriminatory effects
resulted from a state or local agency's issuance
of pollution control permits. The guidance
document also establishes the framework that
EPA's Office of Civil Rights ("OCR") will use
to process complaints filed under Title VI. In
addition, it sets forth the administrative steps
EPA will follow after a complaint is filed and
includes criteria for the Agency to use when
determining the merits of a Title VI
complaint.
Various groups have expressed
concerns with the guidance because it was
drafted with little or no input from state
agencies or the regulated community. In
particular, the Environmental Council of
States ("ECOS") recently raised serious
concerns with the content of the guidance
document and issued a resolution that requests
the Agency to withdraw this version of the
guidance.
Following is an overview of the
procedures and criteria set forth in the interim
guidance document.
Acceptance or Rejection
of the Complaint
Within 20 days of receiving a Title VI
complaint, the OCR will determine whether
a claim should be accepted for further review
or rejected. EPA states that its general policy
is to "investigate all administrative complaints
that have apparent merit" and are timely and
complete. EPA's policy further provides that
under most circumstances a Title VI complaint
must be filed within 180 days of issuance of
the final permit. However, the Agency may
waive this time limit. The interim guidance
indicates that EPA will encourage the parties
to negotiate a settlement after the Agency
accepts a complaint for processing.
Investigation Disparate
Impact Analysis
After EPA accepts a Title VI
complaint, it will conduct an investigation to
determine "whether the permit(s) at issue will
create a disparate impact, or add to an existing
disparate impact, on a racial or ethnic
population." The guidance sets forth a series
of steps that will be used to determine if a
disparate impact has occurred.
First, the OCR will identify the
population affected by the permit that is the
subject of the complaint. EPA indicates that
it believes "proximity to a facility will often be
a reasonable indicator of where impacts are
concentrated." The second step in the analysis
is to determine the racial and/or ethnic
composition of the affected population that
was identified in Step 1. The third step
involves determining what other permitted
facilities, if any, should be included in the
disparate impact analysis. The interim
guidance indicates that the EPA is most likely
to consider Title VI complaints in which "the
permitted facility at issue is one of several
facilities, which together present a cumulative
burden or which reflect a pattern of disparate
impact." EPA goes on to state that "permits
that satisfy the basic public health and
environmental protections contemplated
under EPA's programs nonetheless bear the
potential for discriminatory effects where
residual pollution and other cognizable
impacts are distributed disproportionately to
communities with particular racial or ethnic
characteristics."
After information is gathered in the
first three steps, EPA will use that information
to conduct the disparate impact analysis. EPA
states that this will involve comparing the
racial or ethnic characteristics within the
affected population, as well as comparing the
characteristics of the affected population to the
non-affected population. According to the
guidance, "[t]his approach can show whether
persons protected under Title VI are being
impacted at a disparate rate." The Agency also
indicates that other methods of analysis may
also be used, depending on the facts of the
particular case. The final step in the disparate
impact analysis is to determine whether any
disparity is "significant" by using statistical
analyses. After this step in the analysis is
complete, EPA may make a prima facie
finding that there is a disparate impact or
determine that there is no disparity.
Rebuttal/Mitigation
If EPA issues an initial finding of
disparate impact after conducting the
investigation outlined above, the Agency will
provide the state or local permitting authority
(the recipient of the federal funds) an
opportunity to rebut the finding, justify the
disparate impact, or propose a plan to mitigate
the impact.
Preliminary Finding of
Noncompliance
OCR will issue a preliminary finding
of noncompliance if the recipient fails to
mitigate, rebut, or justify the permitting
action. The interim guidance provides that
EPA is to issue such a finding within 180
calendar days after the investigation is
initiated. The Agency's preliminary finding
may include recommended actions the
recipient can take to remedy the
noncompliance.
Formal Determination of
Noncompliance
After the recipient receives the
preliminary finding of noncompliance, it has
50 days to either achieve compliance
voluntarily or "submit a written response
demonstrating that OCR's preliminary finding
is incorrect." If the recipient fails to take such
actions, EPA will issue a formal determination
of noncompliance. The recipient must come
into compliance within 10 days after receiving
the formal determination. If this is not
accomplished, EPA "will start procedures to
deny, annul, suspend or terminate EPA
assistance" to the recipient, and/or refer the
matter to the Department of Justice for
litigation.
The Agency is accepting public
comment on the interim guidance document
until May 6, 1998. The guidance is available
on the Network's web site in the
"Enforcement" category.
Environmental Groups
Challenge EPA Guidance
Document on
Implementation of Ozone
and PM Standards
On February 27, several environmental
groups filed a petition for review in the
D.C. Circuit challenging an EPA guidance
document addressing implementation of the
ozone and particulate matter (PM) standards in
effect prior to EPA's promulgation of revised
and new ozone and PM standards in July 1997.
Delaware Valley Citizens' Council for Clean Air,
et al. v. EPA (No. 98-1079). That guidance
document, entitled Guidance for Implementing
the 1-Hour Ozone and Pre-existing PM10 NAAQS
(December 1997), explains how EPA plans to
handle the transition from the old standards to
the new standards and sets forth the conditions
under which the old standards will be
revoked. The principal theme of the guidance
document is that states are to maintain their
"momentum" in carrying out existing ozone and
PM programs while they are developing new
programs to implement the revised ozone and
PM standards.
The judicial challenge by the
environmental groups the Sierra Club,
NRDC, the Natural Resources Council of
Maine, as well as the Delaware Valley
Citizens' Council for Clean Air was largely
unexpected. Many industry observers had
regarded the guidance document as relatively
non-controversial for the most part.
The environmental groups' decision to
challenge this guidance document may be
highly significant. It appears to signal the
groups' intention to attack all or most of
EPA's efforts to provide additional flexibility
for states and sources as the Agency
implements the revised ozone and PM
standards. In the July 1997 "Implementation
Plan" accompanying the revised ozone and
PM standards (62 Fed. Reg. 38,421), EPA
stated that it intended to lessen the economic
and administrative impacts of the new
standards by devising flexible, cost-effective
implementation schemes through subsequent
guidance documents and rulemaking
proceedings. For example, EPA announced
that it would create a new category of
"transitional" ozone nonattainment areas that
purportedly would be subject to innovative
new source review requirements and would
likely not be required to implement additional
local controls to meet the revised ozone
standard. EPA has reiterated its intention to
develop flexible implementation schemes for
the new standards many times in various
contexts.
The environmental groups' willingness
to seek review of such a seemingly innocuous
document seems to confirm industry's
concerns that EPA's stated intentions to create
flexible, innovative implementation schemes
might not be carried out. Many industry
representatives believe that, despite EPA's
assurances that workable approaches will be
devised, the final implementation schemes for
ozone and PM will likely end up being much
more rigid than EPA has previously indicated.
It is unclear how EPA will respond to the
environmental groups' attack on the
implementation scheme. EPA may be willing
to compromise with environmental groups on
"flexible" elements of its implementation
schemes to avoid, or settle, litigation or to gain
concessions on other matters. The result may
well be that the flexible elements of the
implementation scheme will not be retained
while the harsher elements of the scheme the
very elements that the flexible elements were
meant to counterbalance will remain intact.
Because a petition for review is not
required to set forth detailed legal arguments
and other documents filed in the case to date
have been preliminary in nature, it is unclear
precisely what legal theories the
environmental groups will rely upon.
However, they generally contend that the
guidance document unlawfully postpones
compliance obligations in certain
nonattainment areas.
EPA Withdraws List of Areas Where
1-Hour Ozone Standard Would Be
Revoked
In a somewhat related development,
EPA recently withdrew a "direct final rule"
setting forth a list of areas where EPA intends
to revoke the 1-hour ozone standard because it
has determined that attainment of that
standard has been achieved. In a Federal
Register notice of January 16, 1998, EPA had
listed hundreds of counties where the 1-hour
standard would be revoked and stated that the
direct final rule containing the list would
become effective in 60 days unless adverse
comments on the rule were received. 63 Fed.
Reg. 2726. However, in a March 16 notice,
EPA stated that, because adverse comments
had been submitted, the direct final rule is
withdrawn and a proposed rule containing the
list will be finalized at some point. 63 Fed.
Reg. 12,652. Among the parties submitting
adverse comments on the direct final rule were
NRDC and the Environmental Defense Fund.
SAVE THE DATE
Clean Air Act Information
Network Spring Meeting,
May 20-21, 1998, Park
Hyatt Hotel, Washington,
D.C.
Send your registration in now by mail, fax
(202-467-7176), or phone (202-467-7878). For
complete details, see the January 1998
Washington Report at WR-175.
Please e-mail any comments or questions to
the Clean
Air Act Information Network.
Return to the Clean Air Act
Information Network Home Page